Report as on: 15/07/2026 11:59 AM
| S.No. | Project Name | Total NRM Works | Total EPA Works | Total Livelihood Works | Total Production Works | Grand Total (NRM+EPA+LIV+PROD) | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |
| 1 | PAPUM PARE-WDC - 1 /2021-22 | 81 | 0 | 22 | 59 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 81 | 0 | 22 | 59 | 0 |
| 2 | PAPUM PARE-WDC - 2 /2021-22 | 56 | 12 | 19 | 25 | 0 | 7 | 0 | 0 | 7 | 0 | 13 | 10 | 0 | 3 | 0 | 14 | 9 | 0 | 5 | 0 | 90 | 31 | 19 | 40 | 0 |
| 3 | PAPUM PARE-WDC - 3 /2021-22 | 90 | 0 | 33 | 57 | 0 | 6 | 0 | 0 | 6 | 0 | 41 | 31 | 0 | 10 | 0 | 48 | 28 | 0 | 20 | 0 | 185 | 59 | 33 | 93 | 0 |
| 4 | PAPUM PARE-WDC - 4 /2021-22 | 19 | 0 | 4 | 15 | 0 | 1 | 1 | 0 | 0 | 0 | 14 | 14 | 0 | 0 | 0 | 22 | 22 | 0 | 0 | 0 | 56 | 37 | 4 | 15 | 0 |
| Total | 246 | 12 | 78 | 156 | 0 | 14 | 1 | 0 | 13 | 0 | 68 | 55 | 0 | 13 | 0 | 84 | 59 | 0 | 25 | 0 | 412 | 127 | 78 | 207 | 0 | |