Report as on: 13/04/2026 10:37 AM
| S.No. | Project Name | Total NRM Works | Total EPA Works | Total Livelihood Works | Total Production Works | Grand Total (NRM+EPA+LIV+PROD) | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |
| 1 | GIRIDIH-WDC - 1 /2021-22 | 526 | 0 | 0 | 190 | 336 | 537 | 0 | 0 | 537 | 0 | 564 | 0 | 0 | 564 | 0 | 223 | 0 | 0 | 223 | 0 | 1850 | 0 | 0 | 1514 | 336 |
| 2 | GIRIDIH-WDC - 2 /2021-22 | 261 | 0 | 2 | 250 | 9 | 135 | 105 | 30 | 0 | 0 | 24 | 0 | 0 | 24 | 0 | 41 | 0 | 37 | 4 | 0 | 461 | 105 | 69 | 278 | 9 |
| Total | 787 | 0 | 2 | 440 | 345 | 672 | 105 | 30 | 537 | 0 | 588 | 0 | 0 | 588 | 0 | 264 | 0 | 37 | 227 | 0 | 2311 | 105 | 69 | 1792 | 345 | |