Report as on: 26/02/2026 01:37 PM
| S.No. | Project Name | Total NRM Works | Total EPA Works | Total Livelihood Works | Total Production Works | Grand Total (NRM+EPA+LIV+PROD) | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |
| 1 | GONDIA-WDC - 1 /2021-22 | 214 | 5 | 0 | 209 | 0 | 26 | 26 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 241 | 238 | 0 | 0 | 3 | 481 | 269 | 0 | 209 | 3 |
| 2 | GONDIA-WDC - 2 /2021-22 | 101 | 52 | 5 | 44 | 0 | 30 | 0 | 30 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 131 | 52 | 35 | 44 | 0 |
| 3 | GONDIA-WDC - 3 /2021-22 | 126 | 48 | 3 | 74 | 1 | 29 | 8 | 21 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | 20 | 0 | 0 | 0 | 175 | 76 | 24 | 74 | 1 |
| 4 | GONDIA-WDC - 4 /2021-22 | 190 | 17 | 0 | 173 | 0 | 26 | 26 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 229 | 229 | 0 | 0 | 0 | 445 | 272 | 0 | 173 | 0 |
| 5 | GONDIA-WDC - 5 /2021-22 | 158 | 4 | 0 | 154 | 0 | 26 | 26 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 277 | 277 | 0 | 0 | 0 | 461 | 307 | 0 | 154 | 0 |
| Total | 789 | 126 | 8 | 654 | 1 | 137 | 86 | 51 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 767 | 764 | 0 | 0 | 3 | 1693 | 976 | 59 | 654 | 4 | |