Report as on: 13/10/2026 07:25 AM
| S.No. | Project Name | Total NRM Works | Total EPA Works | Total Livelihood Works | Total Production Works | Grand Total (NRM+EPA+LIV+PROD) | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |
| 1 | JALGAON-WDC - 1 /2021-22 | 273 | 149 | 0 | 124 | 0 | 26 | 0 | 0 | 26 | 0 | 13 | 13 | 0 | 0 | 0 | 523 | 502 | 0 | 21 | 0 | 835 | 664 | 0 | 171 | 0 |
| 2 | JALGAON-WDC - 2 /2021-22 | 160 | 24 | 0 | 135 | 1 | 19 | 0 | 0 | 19 | 0 | 48 | 48 | 0 | 0 | 0 | 246 | 160 | 0 | 82 | 4 | 473 | 232 | 0 | 236 | 5 |
| 3 | JALGAON-WDC - 3 /2021-22 | 128 | 31 | 0 | 97 | 0 | 26 | 13 | 0 | 13 | 0 | 15 | 15 | 0 | 0 | 0 | 150 | 150 | 0 | 0 | 0 | 319 | 209 | 0 | 110 | 0 |
| 4 | JALGAON-WDC - 4 /2021-22 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 5 | JALGAON-WDC - 5 /2021-22 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Total | 561 | 204 | 0 | 356 | 1 | 71 | 13 | 0 | 58 | 0 | 76 | 76 | 0 | 0 | 0 | 919 | 812 | 0 | 103 | 4 | 1627 | 1105 | 0 | 517 | 5 | |