Report as on: 15/12/2025 11:58 PM
| S.No. | Project Name | Total NRM Works | Total EPA Works | Total Livelihood Works | Total Production Works | Grand Total (NRM+EPA+LIV+PROD) | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |
| 1 | SOUTH WEST KHASI HILLS-WDC - 1 /2021-22 | 337 | 5 | 0 | 332 | 0 | 3 | 0 | 0 | 3 | 0 | 114 | 0 | 0 | 114 | 0 | 77 | 21 | 0 | 56 | 0 | 531 | 26 | 0 | 505 | 0 |
| 2 | SOUTH WEST KHASI HILLS-WDC - 2 /2021-22 | 774 | 320 | 0 | 390 | 64 | 16 | 0 | 0 | 15 | 1 | 120 | 0 | 0 | 120 | 0 | 110 | 30 | 0 | 80 | 0 | 1020 | 350 | 0 | 605 | 65 |
| 3 | SOUTH WEST KHASI HILLS-WDC - 3 /2022-23 | 214 | 30 | 12 | 172 | 0 | 35 | 35 | 0 | 0 | 0 | 17 | 0 | 0 | 17 | 0 | 49 | 49 | 0 | 0 | 0 | 315 | 114 | 12 | 189 | 0 |
| Total | 1325 | 355 | 12 | 894 | 64 | 54 | 35 | 0 | 18 | 1 | 251 | 0 | 0 | 251 | 0 | 236 | 100 | 0 | 136 | 0 | 1866 | 490 | 12 | 1299 | 65 | |