Report as on: 15/07/2026 11:50 AM
| S.No. | Project Name | Sanctioned Project Area (in ha.) | Sanctioned Cost | Fund Utilization | |||||
|---|---|---|---|---|---|---|---|---|---|
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | Fund Received | Total Expenditure (Rs. Crores) | |||||
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 1 | SIRMAUR-WDC - 1 /2021-22 | 3000.0000 | 7.5600 | 0.8400 | 8.4000 | 2.6500 | 0.3000 | 2.9500 | 0.2100 |
| 2 | SIRMAUR-WDC - 2 /2021-22 | 2600.0000 | 6.5520 | 0.7280 | 7.2800 | 0.8100 | 0.0900 | 0.9000 | 0.5800 |
| Grand Total | 5600.0000 | 14.1120 | 1.5680 | 15.6800 | 3.4600 | 0.3900 | 3.8500 | 0.7900 | |