Report as on: 15/12/2025 11:48 PM
| S.No. | Project Name | Sanctioned Project Area (in ha.) | Sanctioned Cost | Fund Utilization | |||||
|---|---|---|---|---|---|---|---|---|---|
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | Fund Received | Total Expenditure (Rs. Crores) | |||||
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 1 | WEST SIANG-WDC - 1 /2021-22 | 2500.0000 | 6.3000 | 0.7000 | 7.0000 | 2.7720 | 0.3080 | 3.0800 | 0.0000 |
| 2 | WEST SIANG-WDC - 2 /2021-22 | 2500.0000 | 6.3000 | 0.7000 | 7.0000 | 3.0870 | 0.3430 | 3.4300 | 0.0000 |
| 3 | WEST SIANG-WDC - 3 /2021-22 | 2000.0000 | 5.0400 | 0.5600 | 5.6000 | 3.6792 | 0.4088 | 4.0880 | 0.0000 |
| 4 | WEST SIANG-WDC - 4 /2021-22 | 2000.0000 | 5.0400 | 0.5600 | 5.6000 | 2.4696 | 0.2744 | 2.7440 | 0.0000 |
| Grand Total | 9000.0000 | 22.6800 | 2.5200 | 25.2000 | 12.0078 | 1.3342 | 13.3420 | 0.0000 | |