Report as on: 13/10/2026 05:57 AM
| S.No. | Project Name | Sanctioned Project Area (in ha.) | Sanctioned Cost | Fund Utilization | |||||
|---|---|---|---|---|---|---|---|---|---|
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | Fund Received | Total Expenditure (Rs. Crores) | |||||
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 1 | KARBI ANGLONG-WDC - 1 /2021-22 | 4700.0000 | 11.8440 | 1.3160 | 13.1600 | 6.2588 | 0.6562 | 6.9150 | 0.0090 |
| 2 | KARBI ANGLONG-WDC - 2 /2021-22 | 3300.0000 | 8.3160 | 0.9240 | 9.2400 | 508.0531 | 0.6024 | 508.6556 | 0.0000 |
| Grand Total | 8000.0000 | 20.1600 | 2.2400 | 22.4000 | 514.3119 | 1.2586 | 515.5706 | 0.0090 | |