S.No. Project Name Sanctioned Project Area (in ha.) Sanctioned Cost Fund Utilization
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores) Fund Received Total Expenditure (Rs. Crores)
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores)
1 2 3 4 5 6 7 8 9 10
1 VIZIANAGARAM-WDC - 1 /2021-22 2839.0000 3.7475 2.4983 6.2458 2.0596 1.3731 3.4327 21.3521
2 VIZIANAGARAM-WDC - 2 /2021-22 2510.0000 3.3132 2.2088 5.5220 1.9323 1.2882 3.2205 23.3202
3 VIZIANAGARAM-WDC - 3 /2021-22 2815.0000 3.7158 2.4772 6.1930 2.4557 1.6371 4.0928 31.8990
Grand Total 8164.0000 10.7765 7.1843 17.9608 6.4476 4.2984 10.7460 76.5713
×