Report as on: 15/12/2025 11:48 PM
| S.No. | Project Name | Sanctioned Project Area (in ha.) | Sanctioned Cost | Fund Utilization | |||||
|---|---|---|---|---|---|---|---|---|---|
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | Fund Received | Total Expenditure (Rs. Crores) | |||||
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 1 | CHAMARAJANAGARA-WDC - 1 /2021-22 | 5322.0000 | 7.0251 | 4.6834 | 11.7085 | 6.7200 | 4.4800 | 11.2000 | 1.2900 |
| 2 | CHAMARAJANAGARA-WDC - 2 /2021-22 | 5103.0000 | 6.7359 | 4.4906 | 11.2265 | 6.4400 | 4.3000 | 10.7400 | 1.0600 |
| 3 | CHAMARAJANAGARA-WDC - 3 /2025-26 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Grand Total | 10425.0000 | 13.7610 | 9.1740 | 22.9350 | 13.1600 | 8.7800 | 21.9400 | 2.3500 | |