Report PE2- Project-wise Mid Term Evaluation of Sanctioned Cost and Fund Utilization


Report as on: 15/12/2025 11:48 PM

S.No. Project Name Sanctioned Project Area (in ha.) Sanctioned Cost Fund Utilization
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores) Fund Received Total Expenditure (Rs. Crores)
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores)
1 2 3 4 5 6 7 8 9 10
1 DAKSHINA KANNADA-WDC - 1 /2021-22 4186.2000 7.0300 4.6900 11.7200 6.7300 4.4800 11.2100 0.1300
2 DAKSHINA KANNADA-WDC - 2 /2021-22 5025.0000 8.4400 5.6300 14.0700 8.0700 5.3800 13.4500 0.0000
Grand Total 9211.2000 15.4700 10.3200 25.7900 14.8000 9.8600 24.6600 0.1300
×