A- A A+ English Hindi
                       
Loading...
Report PE2- Project-wise Mid Term Evaluation of Sanctioned Cost and Fund Utilization


Report as on: 15/07/2026 12:08 PM

S.No. Project Name Sanctioned Project Area (in ha.) Sanctioned Cost Fund Utilization
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores) Fund Received Total Expenditure (Rs. Crores)
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores)
1 2 3 4 5 6 7 8 9 10
1 KUMURAM BHEEM ASIFABAD-WDC - 1 /2021-22 3513.0000 5.9018 3.9345 9.8363 3.2416 2.1610 5.4027 2.4200
2 KUMURAM BHEEM ASIFABAD-WDC - 2 /2021-22 3260.0000 5.4768 3.6512 9.1280 3.1210 2.0806 5.2016 1.1500
3 KUMURAM BHEEM ASIFABAD-WDC - 3 /2021-22 3619.0000 6.0799 4.0532 10.1331 3.7123 2.4748 6.1871 2.3800
4 KUMURAM BHEEM ASIFABAD-WDC - 4 /2021-22 2860.0000 4.8048 3.2032 8.0080 2.6717 1.7812 4.4529 2.8000
Grand Total 13252.0000 22.2633 14.8421 37.1054 12.7466 8.4976 21.2443 8.7500
×