Report PE2- Project-wise Mid Term Evaluation of Sanctioned Cost and Fund Utilization


Report as on: 27/11/2026 07:32 AM

S.No. Project Name Sanctioned Project Area (in ha.) Sanctioned Cost Fund Utilization
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores) Fund Received Total Expenditure (Rs. Crores)
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores)
1 2 3 4 5 6 7 8 9 10
1 ALWAR-WDC - 1 /2021-22 5540.0000 7.3128 4.8752 12.1880 7.3128 4.8752 12.1880 0.1700
2 ALWAR-WDC - 2 /2021-22 5155.0000 6.8046 4.5364 11.3410 6.8046 4.5364 11.3410 0.6500
3 ALWAR-WDC - 3 /2021-22 4956.0000 6.5419 4.3612 10.9031 6.5419 4.3612 10.9031 0.2000
4 ALWAR-WDC - 4 /2021-22 5000.0000 6.6000 4.4000 11.0000 6.6000 4.4000 11.0000 0.4000
5 ALWAR-WDC - 5 /2021-22 5032.0000 6.6422 4.4281 11.0703 6.6422 4.4281 11.0703 0.2100
6 ALWAR-WDC - 6 /2021-22 5656.0000 7.9648 5.3099 13.2747 7.9648 5.3099 13.2747 0.4920
7 ALWAR-WDC - 7 /2021-22 4020.0000 5.3064 3.5376 8.8440 5.3064 3.5376 8.8440 0.4000
Grand Total 35359.0000 47.1727 31.4484 78.6211 47.1727 31.4484 78.6211 2.5220
×