Report PE7- Project-wise Mid Term Evaluation of Mandays Details


Report as on: 15/12/2025 11:53 PM

S.No. Project Name Farmer`s Average Household Income per Annum (Rs. in Lakhs) No. of Farmers Benefited No. of Persondays Generated (man-days)
Pre - Project Status(Aggregate) Mid - Project Status(Aggregate) Controlled Area Project Area Controlled Area Project Area Controlled Area
1 2 3 4 5 6 7 8 9
1 LUNGLEI-WDC - 1 /2021-22 0.0000 0.8500 0.8500 1106 N/A 15714 N/A
2 LUNGLEI-WDC - 2 /2021-22 0.0000 0.7200 0.7200 1271 N/A 12970 N/A
Grand Total 0.0000 1.5700 1.5700 2377 N/A 28684 N/A
×