S.No. Project Name Total Number of Structures Identified for Maintenance Planning Total Number of Structures where Maintenance Work Implemented Total Number of Structures where Maintenance Work Not Implemented
(3-8)
Implementation
Estimated Cost (Rs in Lakhs) for Maintenance Works Expenditure (Rs in Lakhs) for Maintenance Works
Total Estimated Cost Cost from WDF Cost from VB G RAM G/MGNREGA Cost from Other Source (if any) Total Expenditure (11+12+13) Expenditure from WDF Expenditure from VB G RAM G/MGNREGA Expenditure from Other Source
(if any)
1 2 3 4 5 6 7 8 9 10 11 12 13
1 Una-IWMP-1/2009-10 3 3.79 3.79 0.00 0.00 0 3 0 0 0 0
2 Una-IWMP-2/2010-11 0 0 0 0 0 0 0 0 0 0 0
3 Una-IWMP-3/2010-11 9 5.83 5.83 0.00 0.00 0 9 0 0 0 0
4 Una-IWMP-4/2010-11 0 0 0 0 0 0 0 0 0 0 0
5 Una-IWMP-5/2010-11 0 0 0 0 0 0 0 0 0 0 0
6 Una-IWMP-6/2010-11 1 1.37 1.37 0.00 0.00 0 1 0 0 0 0
7 Una-IWMP-7/2012-13 0 0 0 0 0 0 0 0 0 0 0
8 Una-IWMP-8/2012-13 2 2.00 2.00 0.00 0.00 0 2 0 0 0 0
Grand Total 15 12.99 12.99 0.00 0.00 0 15 0 0 0 0