Report as on: 13/04/2026 08:52 AM

S.No. Project Name NRM Works EPA Works Livelihood Works Production Works Total Work Code excluding Foreclosed (NRM(4+5+6) + EPA(8+9+10) + LIV(12+13+14) + PROD(16+17+18)) Total Geotag Work Code Total Non Geotag Work Code (19-20)
Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 JALORE-WDC - 1 /2021-22 1055 192 0 840 12 0 0 12 0 0 0 0 0 0 0 0 1044 400 644
2 JALORE-WDC - 2 /2021-22 423 63 1 355 12 0 0 12 0 0 0 0 0 0 0 0 431 292 139
3 JALORE-WDC - 3 /2021-22 1001 97 34 870 10 1 0 9 0 0 0 0 0 0 0 0 1011 518 493
4 JALORE-WDC - 4 /2025-26 174 89 1 84 0 0 0 0 0 0 0 0 0 0 0 0 174 46 128
Grand Total 2653 441 36 2149 34 1 0 33 0 0 0 0 0 0 0 0 2660 1256 1404