S.No. Project Name NRM Works EPA Works Livelihood Works Production Works Total Work Code excluding Foreclosed (NRM(4+5+6) + EPA(8+9+10) + LIV(12+13+14) + PROD(16+17+18)) Total Geotag Work Code Total Non Geotag Work Code (19-20)
Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 EAST KAMENG-WDC - 1 /2021-22 18 0 0 18 4 4 0 0 10 10 0 0 6 6 0 0 38 14 24
2 EAST KAMENG-WDC - 2 /2021-22 47 12 17 18 0 0 0 0 0 0 0 0 0 0 0 0 47 37 10
3 EAST KAMENG-WDC - 3 /2021-22 10 0 0 10 0 0 0 0 0 0 0 0 0 0 0 0 10 10 0
4 EAST KAMENG-WDC - 4 /2021-22 101 17 1 75 10 0 0 10 29 18 1 10 25 14 0 11 157 98 59
Grand Total 176 29 18 121 14 4 0 10 39 28 1 10 31 20 0 11 252 159 93