Report as on: 04/04/2026 10:16 AM
| S.No. | Project Name | Additional Area Brought Under Irrigation(Ha.) | |||
|---|---|---|---|---|---|
| 2022-23 | 2023-24 | 2024-25 | 2025-26 | ||
| 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | UDAIPUR-WDC - 10 /2025-26 | 0 | 0 | 0 | 0.00 |
| 2 | UDAIPUR-WDC - 11 /2025-26 | 0 | 0 | 0 | 0.00 |
| 3 | UDAIPUR-WDC - 1 /2021-22 | 0.00 | 0 | 0.00 | 0.00 |
| 4 | UDAIPUR-WDC - 2 /2021-22 | 0.00 | 0 | 180.20 | 0.00 |
| 5 | UDAIPUR-WDC - 3 /2021-22 | 0.00 | 0 | 0.00 | 58.00 |
| 6 | UDAIPUR-WDC - 4 /2021-22 | 0.00 | 0 | 78.00 | 0.00 |
| 7 | UDAIPUR-WDC - 5 /2021-22 | 0.00 | 0 | 0.00 | 2.00 |
| 8 | UDAIPUR-WDC - 6 /2021-22 | 0 | 0 | 11.90 | 18.70 |
| 9 | UDAIPUR-WDC - 7 /2021-22 | 0.00 | 0 | 3.00 | 0.00 |
| 10 | UDAIPUR-WDC - 8 /2021-22 | 0.00 | 0 | 31.50 | 0.00 |
| 11 | UDAIPUR-WDC - 9 /2021-22 | 0.00 | 0 | 0.00 | 0.00 |
| Grand Total | 0.00 | 0 | 304.60 | 78.70 | |