Report as on: 04/04/2026 09:03 PM
| S.No. | Project Name | Additional Area Brought Under Irrigation(Ha.) | |||
|---|---|---|---|---|---|
| 2022-23 | 2023-24 | 2024-25 | 2025-26 | ||
| 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | Gomati-WDC - 1 /2021-22 | 0 | 33.00 | 1.65 | 116.00 |
| 2 | Gomati-WDC - 2 /2021-22 | 0 | 13.50 | 0.00 | 78.00 |
| 3 | Gomati-WDC - 3 /2021-22 | 0 | 0.00 | 0.00 | 64.50 |
| 4 | Gomati-WDC - 4 /2022-23 | 0 | 0 | 0 | 64.50 |
| 5 | Gomati-WDC - 5 /2022-23 | 0 | 0 | 0 | 78.50 |
| Grand Total | 0 | 46.50 | 1.65 | 401.50 | |