Report as on: 04/04/2026 08:58 PM
| S.No. | Project Name | Water Harvesting Structures Constructed/Revived(in No.) | |||
|---|---|---|---|---|---|
| 2022-23 | 2023-24 | 2024-25 | 2025-26 | ||
| 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | PURULIA-WDC - 10 /2021-22 | 0 | 15 | 10 | 20 |
| 2 | PURULIA-WDC - 11 /2021-22 | 0 | 24 | 16 | 22 |
| 3 | PURULIA-WDC - 1 /2021-22 | 0 | 22 | 23 | 16 |
| 4 | PURULIA-WDC - 2 /2021-22 | 0 | 18 | 29 | 40 |
| 5 | PURULIA-WDC - 3 /2021-22 | 0 | 33 | 18 | 58 |
| 6 | PURULIA-WDC - 4 /2021-22 | 0 | 22 | 15 | 21 |
| 7 | PURULIA-WDC - 5 /2021-22 | 0 | 10 | 28 | 20 |
| 8 | PURULIA-WDC - 6 /2021-22 | 0 | 12 | 16 | 22 |
| 9 | PURULIA-WDC - 7 /2021-22 | 0 | 10 | 18 | 19 |
| 10 | PURULIA-WDC - 8 /2021-22 | 0 | 5 | 9 | 37 |
| 11 | PURULIA-WDC - 9 /2021-22 | 0 | 8 | 12 | 14 |
| Grand Total | 0 | 179 | 194 | 289 | |