A- A A+ English Hindi
                       
Loading...
Report PE3 - Project-wise Mid Term Project Evaluation of Cropped Area Details
Report PE3 - Project-wise Mid Term Project Evaluation of Cropped Area Details for District 'PATNA' of State 'BIHAR'

Report as on: 16/12/2025 12:31 AM

State Name : BIHAR
S.No. Project Name Gross Cropped Area (ha.) Total Gross Cropped Area (ha.) Area under Plantation Cover (ha.) Area of Culturable Wasteland (ha.)
Kharif Crop Rabi Crop Third Crop Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area
Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 PATNA-WDC - 1 /2021-22 4834.7600 5264.08 513.2900 3268.1200 3545.66 362.3200 55.3200 256.78 17.8800 8158.2000 9066.52 893.4900 0.0000 5.6400 3.2800 771.0000 737.0700 34.7600
Grand Total 4834.7600 5264.08 513.2900 3268.1200 3545.66 362.3200 55.3200 256.78 17.8800 8158.2000 9066.52 893.4900 0.0000 5.6400 3.2800 771.0000 737.0700 34.7600
×