Report PE11 - Project-wise Mid Term Project Evaluation
Report PE11 - Project-wise Mid Term Project Evaluation of Geotagged Work Details


Report as on: 15/12/2025 11:53 PM

State Name : TAMIL NADU,    District Name: KRISHNAGIRI
S.No. Project Name Total Works Total Area of Shape Files Total No. of Geotagged Works
Created Ongoing Completed
1 2 3 4 5 6 7
1 KRISHNAGIRI-WDC - 1 /2021-22 886 52 884 5151.0000 2229
2 KRISHNAGIRI-WDC - 2 /2021-22 910 61 893 6069.0000 2440
3 KRISHNAGIRI-WDC - 3 /2021-22 1112 8 1112 5950.0000 2729
4 KRISHNAGIRI-WDC - 4 /2025-26 0 0 0 0 0
Grand Total 2908 121 2889 17170.0000 7398
×